Upcoming work
As you are aware we have been on site carrying out works to 29 Marylebone Road since December 2023 and the project is progressing well.
As a responsible contractor, we like to keep residents and the wider community aware of upcoming works.
This communication is to inform you that we are due to commence erecting the new steel frame extension from W/C 19.08.24, To facilitate these works we will need to bring in some lifting plant via Bingham Place.
The Delivery of the first crane is expected on Monday 19th August 2024 via Bingham Place with subsequent delivery’s expected throughout the week. Once complete this crane will be removed and replaced with a larger crane on the 27th August 2024 and will be onsite for approximately 4 weeks. During this time, we will be expecting a number of deliveries via Bingham place.
We apologise for any inconvenience caused and should you have any issues or concerns, please contact Julian Morgan Sindall Project Manager on 07580841620 or alternatively Danny, Morgan Sindall Site Manager on 07812 774 070.
Please do visit the 29 Marylebone Road website, for information on the team, updates on the construction work, planned community activities, upcoming opportunities, and newsletters, along with the opportunity for you to ask the project team questions.
This is a highly exciting project for Morgan Sindall and Westminster University, and we are delighted to be working in your borough.