Bedford Passage - December 2024 Newsletter

News |

Welcome...

...to the latest newsletter for the Bedford Passage Development.

A lot has changed since our last communication. We have continued with the façade and internal fit out phase of construction. The roofing installation on level 08 has progressed and the internal services installation is continuing.

As works are continuing at pace on site. We are aiming to maintain regular contact and provide monthly updates of the progress being made at Bedford Passage.

Recent Works

We have been able to make significant progress on the project since our last communication.

This has involved continuing with the façade construction up to level 07 and installation of walls and services to the apartments across all floors.

We are also nearing completion on construction of the scaffold around the building.

Latest progress images

BDF Passage
BDF Passage 2
BDF Passage 3

Details of the upcoming works

Throughout the next few months we will be aiming to continue progressing the façade of the building.

The brickwork and glazing construction is progressing well with works now up to level 07 of the building.

The complete structure reaches eight levels in one area and the rest stands at five storeys and includes a courtyard and communal green space on the roof.

As the façade progresses, construction is also taking shape within the building. Plant is being installed along with other vital building services. Drylining installation is also continuing to progress with the 1st fix stage nearing completion.

During this phase there will be deliveries of drylining, plant, windows and bricks.

These deliveries will continue to enter the site via the Bedford Passage.

Community Engagement

Over the last month, we have been engaging with numerous activities and events.

We had the pleasure of hosting two students from Westminster Kingsway College for work experience. During their time with us, they gained valuable insights into both on-site and off-site operations. They thoroughly enjoyed their experience and now have a deeper understanding of the construction industry.

Every six months, Bedford Passage organizes health checks for everyone working on site. These comprehensive tests are an excellent way to ensure that our workers maintain good health, benefiting both their well-being and the overall safety of our site.

This year, we had the privilege of collaborating with Wrap Up London, supporting their annual winter coat campaign by donating coats. Over the past 14 years, Wrap Up London has been providing much-needed coats to individuals experiencing homelessness.